Friday, June 24, 2011

Plumbing Recap

Ok, so lets go over this again.


This is BAD...




This is GOOD...




Now that we've cleared up any confusion lets move on.

All the inside plumbing  is done.


Hand Sink


3 Compartment Sink





All that's left is the outside "mop sink" plumbing, which, if my husband has anything to do with it will be finished by lunch time!



Speaking of the Angel....



It's 8:45am  ... he's ahead of schedule.



Thursday, June 23, 2011

Elloree is Blooming

The Crepe Myrtles are in full bloom.














Wednesday, June 22, 2011

Oh, Crap!

If anyone's wondering if you can duct tape plumbing pipes together I have an answer for you. Yes, you can. You shouldn't, but you can. It's been done before.

Needless to say we hit a snafu with the plumbing. The new sinks had to be plumbed, and the only way to access the existing plumbing which is under the false bathroom floor was THROUGH the bathroom floor. So, we had to cut a hole. Then ... we saw this.



MacGyver's Duct Tape Trick


Which made us have to cut a bigger hole..... 




Thank you God for all the people that love me. Speaking of the people that love me, here's one of them.
 
elbow deep in crap pipes
 


...and here's the other one peeking out from behind the monster sink (more on that later).


Arif Baig



 I love y'all too!

Monday, June 20, 2011

Electrifying News.

The electrical rough-in inspection PASSED! Whoo Hoo!



The final inspection won't happen till all the dry-wall, and fixtures are up. But for right now, Whoo Hoo!

Thursday, June 16, 2011

Moving Right Along

So, most of the electrical is done. We just have to put up the fixtures once the sheet rock(ing) is completed. The kitchen lights, however, are up giving us more than the recommended candles of light.

Future Kitchen
Panel Box

That's ALOT of wire for an itty bitty space!